英国财政部Standardisation of PFI Contracts介绍/李继忠(7)
8.3 Examples of Unavailability
8.4 Payment for Availability and Weighting of Critical Areas
8.5 When does Availability Commence?
8.6 When does Unavailability Commence?
8.7 Rectification of Unavailability
8.8 Service Unavailable but Used
8.9 Restoration of Availability
8.10 Planned Maintenance
Chapter 9 PERFORMANCE REQUIREMENTS
9.1 Introduction
9.2 Setting the Performance Level
9.3 Replacement of Sub-Contractors
9.4 Monitoring of Sub-Contractors
9.5 Consequences of Poor Performance
Chapter 10 PAYMENT MECHANISM MANAGEMENT AND MONITORING
10.1 Contract Management
10.2 Monitoring against the Payment Mechanism
10.3 Commencement of Monitoring
10.4 Who does the Monitoring?
10.5 Who pays for the Monitoring?
10.6 Reporting the Results of Monitoring
Chapter 11 MAINTENANCE
11.1 Introduction
Clause 11.1 Maintenance
11.2 Sinking Fund
11.3 Expiry of the Contract
11.4 Transfer of Assets at End of Contract
11.5 Surveys
Clause 11.5 Surveys
Chapter 12 PAYMENTS AND SET-OFF