法律图书馆>>法律论文资料库>>全文
英国财政部Standardisation of PFI Contracts介绍/李继忠(7)
8.3 Examples of Unavailability
8.4 Payment for Availability and Weighting of Critical Areas
8.5 When does Availability Commence?
8.6 When does Unavailability Commence?
8.7 Rectification of Unavailability
8.8 Service Unavailable but Used
8.9 Restoration of Availability
8.10 Planned Maintenance

Chapter 9 PERFORMANCE REQUIREMENTS

9.1 Introduction
9.2 Setting the Performance Level
9.3 Replacement of Sub-Contractors
9.4 Monitoring of Sub-Contractors
9.5 Consequences of Poor Performance

Chapter 10 PAYMENT MECHANISM MANAGEMENT AND MONITORING

10.1 Contract Management
10.2 Monitoring against the Payment Mechanism
10.3 Commencement of Monitoring
10.4 Who does the Monitoring?
10.5 Who pays for the Monitoring?
10.6 Reporting the Results of Monitoring

Chapter 11 MAINTENANCE

11.1 Introduction
Clause 11.1 Maintenance
11.2 Sinking Fund
11.3 Expiry of the Contract
11.4 Transfer of Assets at End of Contract
11.5 Surveys
Clause 11.5 Surveys

Chapter 12 PAYMENTS AND SET-OFF


总共18页     [1]   [2]   [3]   [4]   [5]   [6]   7   [8]   [9]   [10]   [11]   [12]   [13]   [14]   [15]   [16]   [17]   [18]  
上一页     下一页    

声明:本论文由《法律图书馆》网站收藏,
仅供学术研究参考使用,
版权为原作者所有,未经作者同意,不得转载。
法律图书馆>>法律论文资料库